竣工三峡左岸电站2005年9月16日上午9点23分,三峡左岸电站经过三峡建设者两年零二个月的艰苦努力,最后一台机组9号机正式并网发电。这标志着三峡左岸电站比原定工期提前一年全面投产,标志着三峡左岸电站机电工程全部完工。三峡电站概况三峡左岸电站装机14台,总容量980万kW。全
Completion of the Three Gorges Left Bank Power Station On September 16, 2005, at 9:23 am, the left bank power station of the Three Gorges Project passed the arduous efforts of the Three Gorges Project builders for two years and two months and the last unit No. 9 was officially connected to the grid. This marks the full operation of the Three Gorges Left Bank Power Station one year earlier than originally scheduled, marking the completion of the mechanical and electrical engineering of the Three Gorges Left Bank Power Station. Three Gorges Power Station Overview Three Gorges left bank installed capacity of 14 units, with a total capacity of 9.8 million kW. all