2007年8月2日,某钢铁有限公司炼钢厂1#转炉主控楼交联电缆室发生一起事故,事故造成炼钢厂多部门电源、通讯、仪表线路中断,电线电缆烧毁,损失严重,使炼钢厂停止冶炼,导致公司全线停产。炼钢厂1#转炉主控楼交联电缆室是1#转炉倾动、氧枪电控和天车
On August 2, 2007, an accident occurred in the cross-linked cable room of the main control building of No. 1 converter in a steel mill of Steel Co., Ltd. The accident caused the power supply, communications and instrument lines of the steel mills to be cut off, the wires and cables were destroyed, Steel smelting stop, resulting in the company cut-off across the board. Steel Works 1 # converter control building cross-linked cable room is 1 # converter tilting, oxygen gun electric control and crane