“5.12”地震发生后,映秀湾水电站道路、通讯一度中断,首部枢纽、引水隧洞、厂房(生活区)、尾水渠均遭受严重损坏。我部自2008年7月1日进场后,首先承担了映秀湾水电站首部枢纽、引水隧洞、厂房、尾水等4个重点部位、共12个大项、80个小项的恢复重建工作。映秀湾水电站原计划于2009年3月完成首台机组发电目标,但在映秀湾水力发电总厂、成都勘测设计研究院、四川水电工程建设监理有限工程、武警部队党委的正确领导和支持下,项目部积极组织人员、设备投入到恢复生产工作中,围绕“12月31日首台机组发电目标”展开了5个月的攻坚战。对映秀湾水电站恢复生产工程中重点部位的施工工作进行了总结。
“5.12 ” After the earthquake, Yingxiuwan hydropower station roads, communications was interrupted, the first hub, diversion tunnel, plant (living area), tailings have been severely damaged. After entering the scene on July 1, 2008, the Ministry of Commerce took over the reconstruction of the first key project of Yingxiuwan Hydropower Station, the diversion tunnel, the factory building, and the tail water. There were a total of 12 major projects and 80 minor projects. Yingxiuwan Hydropower Station originally planned to complete the first unit generating target in March 2009, but with the correct leadership and support of the Yingxiuwan Hydropower Plant, Chengdu Survey Design and Research Institute, Sichuan Hydropower Engineering Construction Supervision Limited Project and Armed Police Forces Party Committee, Project Department actively organize personnel, equipment investment in the restoration of production work, around the “December 31 first unit power generation targets” launched a five-month battle. The construction work of the key parts in the restoration production project of Yingxiuwan Hydropower Station was summarized.