该项目混凝土总方量37万m~3,其中泵送量20万m~3,预计施工2年,平均每月泵送量1.5万m~3,混凝土搅拌运输车11台,运距最远3km,高峰期时几处同时浇注,以每台泵车最少配4台混凝土搅拌运输车计算,高峰期可以用到4台泵车。模式一:单月租赁,每月8万元,2年192万元租赁费。模式二:每立方18元泵送费,假设每次泵送量在100m~3以上,20万m~3泵送费用约为360万元。模式三:假设每月泵送量在3000m~3以上,费用同上。
The total volume of concrete in this project is 370,000 m 3, of which the pumping capacity is 200,000 m 3. The expected construction period is 2 years with an average monthly pumping volume of 15,000 m 3 and 11 concrete mixing trucks with the farthest distance 3km, at the same time several peaks at the same time pouring, with each pump at least 4 concrete mixer truck calculation, peak pump 4 can be used. Mode one: single month lease, 80,000 yuan per month, 2 years 1.92 million yuan rental fee. Mode 2: 18 yuan per cubic pumping costs, assuming that the amount of each pumping more than 100m ~ 3, 200,000 m ~ 3 pumping costs about 3.6 million yuan. Mode 3: Assuming a monthly pump volume of 3000m ~ 3 above, the same cost.