对于在稳固的矿岩中掘进高度为20米以下的天井,我矿采用丁一种新的施工措施—挂梁掘进天井。其施工工艺为: 使用YSP—45凿岩机进行常规的打眼爆破,当天井高度腕2米时,随天井凿岩在距井口高1米处的井壁四角各打一深度为50—60厘米深的下向孔,插入挂桩,并用楔子加固(为减小冲击破坏,挂桩应侧装);待下一循环天井掘进时,在挂桩上挂上挂梁(每一平台使用两副挂梁),铺上板子并用活动插销使梁与板固定即可进行凿岩。当向上孔凿完后,在井壁四角距下一台挂桩孔垂高1.2米处再打挂桩孔,并安装挂桩,然后装药联线,撤去台板、挂梁至安全地带存放好
For mines with a height of less than 20 meters in a stable rock, our mine uses a new type of construction—hanging beams to tunnels. The construction process is as follows: Use the YSP-45 Rock Drill to perform normal drill blasting. When the height of the nadir is 2 meters, drill a depth of 50-60 centimeters deep with four corners of the shaft wall at a height of 1 meter from the wellhead. Down the hole, insert the pile, and use the wedge reinforcement (in order to reduce the impact damage, the pile should be installed side by side); when the next cycle of tunnel excavation, hang up the hanging beam on the hanging pile (each platform uses two sets of hanging beam ), rock the board by placing the board and fixing the beam to the board with movable latches. When the upward hole is drilled, hang the pile hole at the corner of the borehole 1.2 meters from the height of the next hanging pile hole, install the pile, and then install the drug line, remove the platen, hang the beam to the safe zone to store it is good