根据世界风能协会报告,截止2012年上半年,中国风电机组装机容量达到了67.774 GW,而据中国风能协会统计,截止2012年底,我国最终实现并网的风电只达到了52.58 G W。对比上述两个数据可知,仅在2012年我国至少有15 GW的风电没能实现并网发电,造成了巨大的资源浪费。风电并网面临的诸多问题大体可分为两个方面:一是风电机组及
According to the report of World Wind Energy Association, the installed capacity of wind turbines in China reached 67.774 GW by the first half of 2012. According to the statistics of the China Wind Energy Association, by the end of 2012, the wind power in China that finally achieved grid connection reached only 52.58 GW. Comparing the above two data, we can see that in 2012 alone, at least 15 GW of wind power in our country failed to achieve grid-connected generation, resulting in huge waste of resources. Many problems facing wind power integration can be divided into two aspects: First, wind turbines and