在泄水闸或溢流堰与后接陡槽之间,为了使二者底坡上水流平顺,达到水流紧贴坡底面,常选用抛物线或圆弧线段来连接。对于大中型水利水电工程,连接段曲线,需由水工模型试验确定,但对尚处于初期设计阶段的大中型工程,或小型水利水电工程,在缺乏水力试验资料的情况下,常参考已建工程先例进行类比拟设。参考书中,提出若无试验资料时,可采用如下抛物线方程式(见图)。
Between the sluice gate or overflow weir and the subsequent chute, in order to smooth the flow of water on both sides of the slope, the water flows close to the bottom of the slope, often using parabolas or arc segments to connect. For large and medium-sized water conservancy and hydropower projects, connecting section of the curve, hydraulic model test to be determined, but still in the early design stage of large and medium-sized projects, or small-scale water conservancy and hydropower projects in the absence of hydraulic test data, often refer to the built Engineering precedent for analogy. Reference book, proposed without test data, the following parabolic equation can be used (see Figure).