大华衬衫厂生产楼1~5层顶板饰面作法为: (1)钢筋混凝土预制板构缝,1:0.3:3水泥白灰膏砂浆打底、玻璃丝灰(略加水泥)罩面; (2)板底腻子刮平; (3)喷大白浆。该项工程工期要求紧,油漆刷浆饰面的工程量比较大,1~5层顶板刮腻子需要300个工日,加上油漆饰面工程,当时施工力量,远不能满足生产上的需要。为了组织好该项工程的竣工,我们经过三结合研究,决定把室内混凝土顶板刮腻子,由手工操作改为机械喷涂。
Dahua shirt factory production floor 1 to 5 roof cover practice as follows: (1) reinforced concrete prefabricated plate joints, 1:0.3:3 cement white plaster mortar base, glass fiber ash (slightly cement) cover; (2 ) Screed putty on the bottom of the board; (3) Spray large white pulp. The construction period of the project is tight, and the amount of paint and brush facing is relatively large. The 1 to 5 layers of top scraping putty require 300 working days. With the paint finishing project, the construction strength at that time is far from meeting the production needs. In order to organize the completion of the project, we conducted a three-pronged study and decided to put the indoor concrete roof scraping putty by manual operation instead of mechanical spraying.