Colbun 坝为斜心墙砾石坝,筑于最大厚度达68米的冲积层上,坝高116米,填筑量1400万立方米,于1984年4月建成。鉴于坝建在地震区而基础透水性高,压缩变形又大,所以基础防渗采用塑性混凝土防渗墙,墙厚1.20米,长335米,平均高度38米,最大高度68米,垂直而积12800平方米。于1981年11月挖槽孔、1982年8月全部完成。塑性混凝土每立方米的配合比为:
The Colbun Dam is a sloping gravel dam built on an alluvium of 68 meters in maximum thickness, 116 meters high and 14 million cubic meters of reclaimed land, completed in April 1984. In view of the dam built in the earthquake zone and the foundation of high permeability, compression deformation and large, so the basic impervious plastic concrete cutoff wall, the wall thickness of 1.20 meters, 335 meters long, an average height of 38 meters, the maximum height of 68 meters, vertical and plot 12800 square meters. Dig hole in November 1981, completed in August 1982. Plastic concrete per cubic meter with the ratio of: