济南燕子山实验住宅小区施工中,组织了山东省施工质量竞赛,推行全面质量管理。参加小区住宅楼建设的共有33支施工队伍,承建了54幢住宅楼,共计16.7573万平方米。1987年5月至7月先后开工,当年11月25日停工,1988年4月20日正式复工,自6月20日以后相继竣工,至9月23日全部竣工验收。推行全面质量管理的主要情况如下:一、对参赛施工队伍实行方针目标管理建设部对燕子山实验住宅小区的要求是“从规划、设计全面考虑通风与保温的特点,应用新技术、新设计进行综合开发,提高建筑物功能与质量,开展施工优质竞赛,为我国气温过渡区新一代住宅小区建设提供新的经验”。
During the construction of the experimental Yanzishan Residential Quarter in Jinan, Shandong Province organized a quality competition for construction and implemented total quality management. A total of 33 construction teams participated in the construction of residential residential buildings, and 54 residential buildings were constructed, totaling 167,573 square meters. From May to July 1987, it started work and was suspended on November 25 of that year. It was formally resumed on April 20, 1988. It was completed after June 20th and completed and accepted on September 23. The main conditions for the implementation of total quality management are as follows: 1. Implementation of guidelines for the participating construction teams Objectives Management The requirements of the Ministry of Construction for the Yanzishan Experimental Residential Community are: “Comprehensively consider the characteristics of ventilation and heat preservation from planning and design, and apply new technologies and new designs. Comprehensive development, improve the function and quality of buildings, carry out construction quality competitions, and provide new experiences for the construction of a new generation of residential communities in China’s temperature transition area.”