南昌钢铁厂根据本厂焦丁充裕的条件,在255m~3全生矿高炉上组织进行了矿石焦丁混装试验,取得了满意的效果。在为期一周的试验期内,每吨铁掺焦丁32kg,高炉入炉比下降了40公斤,高炉利用系数提高0.1,综合折算入炉焦比接近国家等级炉标准。随后,列入了正常生产工艺,自六月一日至十二月底,七个月内共加入毛焦丁3077.48t,相当于加入干焦丁2769.25吨,按最低置换比0.8计算,共节约焦炭2215.4吨,实际节约燃料费37.66万元。
Nanchang Iron and Steel Plant under the conditions of adequate Jiao Ding, 255m ~ 3 all-mine blast furnace ore coke Ding mixed test, and achieved satisfactory results. During the week-long trial period, 32kg of iron was added per ton of iron, 40kg of which was lowered in the blast furnace and 0.1 in the blast furnace. The conversion rate into the furnace-coke ratio was close to the national standard for furnaces. Subsequently, included in the normal production process, from June 1 to the end of December, within a total of 3 months, Mao Ding Ding 3077.48t, equivalent to adding dry coke 2769.25 tons, according to the lowest replacement ratio of 0.8 calculated to save coke 2215.4 tons, the actual fuel savings 376,600 yuan.