2014年10月5日,正值国庆假期,杭氧神华宁煤项目现场人头攒动,杭氧神华宁煤项目部所有人员放弃节假日休息时间,自发来到现场见证一个重要的时刻——杭氧神华宁煤项目第一套10万m3/h空分设备冷箱封顶。从08:00开始,现场所有施工人员做着吊装前的准备工作。由于最后一层冷箱板采用整体吊装,吊装的难度很大。一组现场施工人员根据吊车的站位和冷箱的位置提前模拟预演、规划好即将行进的路线。另一组人员正在对冷箱的四个角进行吊块的最后焊接固定工作。起重工按照起
October 5, 2014, coincided with the National Day holiday, hangzhou Shenhua coal project site full of people, Hanguxiang Shenhua Coal Project Department to give up all the staff to rest during the holiday, spontaneously came to the scene to witness an important moment - Hangxiao Shenhua Ning Coal project first set of 100,000 m3 / h air separation plant cold box cap. Starting from 08:00, all construction workers on site are doing the preparatory work before hoisting. As the last layer of cold plate with the overall lifting, lifting a great difficulty. A group of on-site construction workers according to the location of the crane station and cold box simulation rehearsal in advance planning the upcoming route. Another group of staff are on the cold box of the four corners of the final welding block hanging work. Crane in accordance with