论文部分内容阅读
窝工补偿主要包括工期补偿和经济补偿,在补偿费用计算中因涉及面较多,目前并无统一规则。在合同条件下,只有处于关键线路上的时间延误才能得到工期补偿;窝工人数及单价的计算包括生产人员及管理人员;停置机械的计算按每昼夜一个台班核算,同时合理考虑调配因素;停置机械台班费不含额外投入的机械,非承包商原因造成机械停置,应属设备停置;停工管理费的计算包括现场管理费和公司管理费。
Welfare compensation mainly includes construction period compensation and economic compensation. There are currently no uniform rules in the calculation of compensation fees due to more involved aspects. Under the contractual conditions, only the delay in the time of the key routes can be compensated for the duration of construction; the number of workers and unit price calculation includes the production staff and management personnel; the calculation of parked machinery is calculated on a daily basis and on a daily basis while rationally considering the factors ; Stop mechanical shift costs do not include additional investment in machinery, non-contractors cause mechanical stoppage, should be equipment stop; stop management fee calculation includes site management fees and company management fees.