为实现黄河下游1999年确保花园口站22000m3/s洪水时大堤不决口和确保小浪底工程安全施工的防汛目标,制定了小浪底工程1999年度汛目标和加快工程施工进度安排的计划,重点分析了三门峡水库自然调洪和控制运用条件下小浪底工程调度方案和水库调洪在下游防洪中的作用,提出黄河防汛中应注意的问题。
In order to realize the flood control goal of ensuring the safety of Xiaolangdi Project during the flood season of Huayuankou Station in 1999 in the lower reaches of the Yellow River and ensuring the safe construction of Xiaolangdi Project, the plan of Xiaolangdi Project for flood season in 1999 and schedule for speeding up construction was formulated. Reservoir natural flood control and control under the conditions of Xiaolangdi project scheduling and reservoir flood control in the role of downstream flood control, the Yellow River flood control should pay attention to the problem.