以张家界荷花机场航站楼工程为背景,结合工程的技术难度大、施工周期短等特点及施工现场的实际情况,对航站楼主楼屋顶网架拔杆提升施工法的安装工艺流程、安装要点、整体验算分析等进行了较为详细的阐述,并提出了施工中应注意的关键问题。同时对网架关键节点的挠度进行施工过程与围护结构施工后监测,监测结果均满足相关规范要求。实践证明:该网架工程采用提升施工技术进行安装,达到了结构稳定、经济指标合理、施工安全等要求,减少了施工现场脚手架搭设的工作量,为航站楼工程其他专业交叉施工赢得了时间,同时减少了大量的高空焊接作业,取得了良好的综合效益。
Taking Zhangjiajie Lotus Airport Terminal Project as a background, combined with the technical difficulties of the project, the short construction period and the actual conditions at the construction site, the installation procedure and installation points of the lifting method of the roof grid of the terminal building , The overall checking and analysis conducted a more detailed description, and put forward the construction of the key issues to be noticed. At the same time, the construction process of the deflection of the key nodes of the grid and the monitoring after the construction of the envelope are monitored, and the monitoring results all meet the relevant specifications. The practice proves that the grid construction is installed by using the upgrade construction technology and meets the requirements of structural stability, reasonable economic indicators and construction safety, reducing the workload of setting up scaffolding at the construction site and winning the time for cross-construction of other specialties of the terminal building project , While reducing a large number of high-altitude welding operations, and achieved good overall benefits.