某项目部施工的小区2号楼剪力墙结构,地下2层,地上28层,建筑面积19660.10m~2,一梯四户,是三类高层住宅建筑。5层主体结构用C35混凝土229m~3,浇筑时间为1月22日,从中午12点开始,到晚上18点浇筑完成。浇筑当天,天气预报有寒流,项目部管理采取的措施及施工过程如下。一、施工过程1.防风蓄热措施
Building construction of a project by the Ministry of Building 2 shear wall structure, 2 underground, 28 above ground, construction area of 19660.10m ~ 2, a ladder four, is three types of high-rise residential buildings. The main structure of the 5-story C35 concrete with 229m ~ 3, pouring time is January 22, starting from 12 noon, pouring completed at 18:00. Pouring the same day, the weather forecast cold, the project management measures taken and the construction process is as follows. First, the construction process 1. Wind and heat storage measures